This is Phase 1 of a three stage programme of road and cycle improvements to the A180 and its link roads. This phase will deliver essential maintenance to two key industrial roads directly linked to A180: Moody Lane and Woad Lane, and increase sustainable travel options for cyclists and pedestrians, within key employment zones.
Both roads (Moody Lane and Woad Lane) lead to important employment sites in Grimsby, access to the Port of Grimsby and both link to the junction of the planned new industrial link road – the Humber Link Road. This road will connect key EZ sites and other industrial areas with the Ports and the new shared use cycle/footway will complete the off-road routes for cyclists travelling through to the Immingham industrial area.
Project Dates
March 1, 2019 - January 31, 2020
Project Sponsor
North East Lincolnshire Council
Location
Moody Lane and Woad Lane, Grimsby
Funding
Total project expenditure – £2,622,110.00
LGF Spend:
- Contracted – £2,094,688.00
- Achieved to date – £203,887.00
Public Spend:
- Contracted – £524,422.00
- Achieved to date – £0
Private Spend:
- Contracted – £3,000.00
- Achieved to date – £0
Outputs
Construction Jobs:
- Contracted – 36
- Achieved to date – 10
Resurfaced roads (Km):
- Contracted – 2.81
- Achieved to date – 0
New cycleways completed and open for public use (Km):
- Contracted – 1.25
- Achieved to date – 0
Resurfaced footway (m):
- Contracted – 3,230
- Achieved to date – 0
Resurfaced shared use cycle/footway (m):
- Contracted – 900
- Achieved to date – 0
Approval Status
Business case approved
Delivery Status
Started
All locations are approximate.