Brough Relief Road (BRR) is an essential piece of infrastructure that links the new Brough South Development with the western side of Brough while also providing a new access for the Humber Enterprise Park (HEP) Enterprise Zone site.

 

This is the last piece of the infrastructure jigsaw that will create 0.7 km of new public highway and unlock 85 ha of employment land (35 ha of which has EZ status), creating 800 new jobs and accelerating the delivery of 550 housing units, 17,243 sqm of commercial space (A & B class uses), 4,088 sqm of community space (D1 & D2 uses) and improved public realm. It will also reduce HGV and other traffic through Brough Town Centre.

‘Brough South’ led by the Horncastle Group and HEP led by Citivale are two employment related projects that have the potential to transform the growing town of Brough and make a significant contribution to the local and regional economy. To date the developments have been progressed in isolation but share a common infrastructure constraint which is access.

 

 

Project Dates

November 1, 2019 - July 31, 2020

Project Sponsor

East Riding of Yorkshire Council

Location

The scheme is located to the south east of the town of Brough in the East Riding of Yorkshire within the former Brough Aerodrome site on land controlled by Horncastle Group as part of the wider Brough South mixed use development and Citivale as part of the Humber Enterprise Park Enterprise Zone site. The project area is linear and extends for approximately 0.8 km in a roughly east-west direction from approximate National Grid Reference (NGR) SE941 262 at the western extent to NGR SE948 261 at the eastern extent. The closest postcode to the site is HU15 1ER.

Funding

Total project expenditure – £6,521,885.00

LGF Spend:

  • Contracted – £3,260,943.00
  • Achieved to date – £0

Public Spend:

  • Contracted – £1,630,471.00
  • Achieved to date – £0

Private Spend:

  • Contracted – £1,630,471.00
  • Achieved to date – £0

 

Outputs

New Jobs:

  • Contracted – 600
  • Achieved to date – 0

Construction jobs:

  • Contracted – 150
  • Achieved to date – 0

Housing units started:

  • Contracted – 550
  • Achieved to date – 0

Housing units completed:

  • Contracted – 550
  • Achieved to date – 0

Number of homes with improved broadband:

  • Contracted – 550
  • Achieved to date – 0

New Roads (Km):

  • Contracted – 0.7
  • Achieved to date – 0

New cycleways completed and open for public use (Km):

  • Contracted – 0.7
  • Achieved to date – 0

Area of land reclaimed/redeveloped or reassembled (ha):

  • Contracted – 85
  • Achieved to date – 0

Commercial floor space created (sq.m.):

  • Contracted – 17,243
  • Achieved to date – 0

Commercial floor space occupied (sq.m.):

  • Contracted – 17,243
  • Achieved to date – 0

Area of land with reduced flood risk (ha):

  • Contracted – 50
  • Achieved to date – 0

 

Approval Status

Business case submitted

Delivery Status

In development

Last updated: August 21, 2019