Highways England’s A63 Castle Street Major Scheme includes funding to provide a ‘standard’ motorway style footbridge over A63 Castle Street to link the City Centre with the prime waterfront and Fruit Market regeneration sites. This project is to provide funding for an enhanced ‘iconic’ bridge crossing to the Marina area.
Project Dates
April 1, 2017 - July 31, 2020
Project Sponsor
Hull City Council
Location
A63 Hull between Princes Quay and Hull Marina (HU1 1PS)
Funding
Total project expenditure: £14,894,722
LGF Spend:
- Contracted – £4,000,000
- Achieved to date – £4,000,000.00
Public Spend:
- Contracted – £10,894,722
- Achieved to date – £11,193,174.00
Outputs
Construction Jobs:
- Contracted – 741
- Achieved to date – 85
New shared pedestrian/cycleway completed and open for public use (2 ramps of 0.121 Km each – 0.242Km in total) & New A63 Bridge (0.0378 Km):
- Contracted – 0.279
- Achieved to date – 0
Approval Status
Business case approved
Delivery Status
Started
View project homepageAll locations are approximate.