Hull’s housing-led renewal programme is very well established and incorporates a range of private, community sector and registered provider (RP) partners, which ensures that it is best placed to deliver transformation of the housing market in Hull. Following the success of previous phases of the programme, a large pipeline of sites has been identified to unlock delivery of both new build housing and schemes to refurbish housing post-2018.

Aligning with national priorities the greatest opportunity of the programme is through new build sites where up to 1,000 homes for open market sale and affordable rent will be un-locked for development through investment in flood mitigation, site remediation and tackling adverse ground conditions. The empty homes programme will continue its momentum and will address a further 100 empty properties. The 100 homes represents a significant number of the more challenging and persistent empties in the city.  The private sector renewal programme will deliver frontage improvements and energy efficiency improvements in prioritised areas.  This would deliver  approx.700 direct jobs, 1,000 indirect jobs and more than 100 apprenticeships over the lifetime of the programme.

Project Dates

September 1, 2018 - March 31, 2029

Project Sponsor

Hull City Council

Location

Across the City of Hull, HU1 – HU9

Funding

Total project expenditure – £44,720,665.00

LGF Spend:

  • Contracted – 4,000,000.00
  • Achieved 2018/19 – £634,000.00

Public Spend:

  • Contracted – £40,720,665.00
  • Achieved 2018/19 – £722,227

Outputs

Apprenticeships created:

  • Contracted – 135
  • Achieved to date – 0

Construction Jobs:

  • Contracted – 906
  • Achieved to date – 0

Level 2 qualifications achieved:

  • Contracted – 110
  • Achieved to date – 0

Housing Units started:

  • Contracted – 1,437
  • Achieved 2018/19 – 34

Housing units completed:

  • Contracted – 1,437
  • Achieved 2018/19 – 28

Resurfaced roads (Km):

  • Contracted – 1.15
  • Achieved to date – 0

New Roads (Km):

  • Contracted – 0.2
  • Achieved to date – 0

Level 3 qualifications achieved:

  • Contracted – 27
  • Achieved to date – 0

Area of land reclaimed/redeveloped or reassembled (ha):

  • Contracted – 37.5
  • Achieved to date – 0

Housing units completed that will be at an affordable rent:

  • Contracted – 339
  • Achieved 2018/19 – 34

New completed dwellings at Council Tax Band B:

  • Contracted – 856
  • Achieved to date – 0

New completed dwellings at Council Tax Band A:

  • Contracted – 100
  • Achieved 2018/19 – 34

New completed dwellings at Council Tax Band C:

  • Contracted – 144
  • Achieved to date – 0

New completed dwellings not analysed for Council Tax Band:

  • Contracted – 337
  • Achieved to date – 0

 

 

Approval Status

Business case approved

Delivery Status

Started

View project homepage

Last updated: August 12, 2019

All locations are approximate.

Priorities
An infrastructure that supports growth
An infrastructure that supports growth
Read more