Specialist managed workspace building targeting business and professional services to support the development of environmental technologies sector (renewables, low carbon industries etc) on both banks of the Humber.

The ERGO centre is an integral part of the wider Bridegehead development site which has the potential to support up to 3000 jobs over its lifetime. ERGO will be the focal point of the wider site for services and added value activities.

CASE STUDY – ERGO  PHOTOS – ERGO

Project Dates

December 1, 2016 - September 4, 2017

Project Sponsor

East Riding of Yorkshire Council

Location

Bridgehead Business Park, Hessle, East Riding of Yorkshire, HU13 0GD

Funding

Total Project Expenditure – £4,015,417.00

LGF Spend:

  • Contracted – £1,000,000.00
  • Achieved 2015/17 – £1,000,000.00

Public Spend:

  • Contracted – £3,015,417.00
  • Achieved 2015/17 – £1,934.00
  • Achieved 2017/18 – £2,908,292.00
  • Achieved 2018/19 – £105,191.00.00

 

 

Outputs

New Jobs:

  • Contracted – 1
  • Achieved pre 2018/19 – 5

Safeguarded Jobs:

  • Contracted – 48
  • Achieved re 2018/19 – 0
  • Achieved 2018/19 – 48

Construction Jobs:

  • Contracted – 15
  • Achieved Pre 2018/19 – 0
  • Achieved 2018/19 – 124

Area of land reclaimed/redeveloped or reassembled (ha)

  • Contracted – 0.62
  • Achieved Pre 2018/19 – 0.62

Commercial floor space created (sq.m.)

  • Contracted – 2,154
  • Achieved Pre 2018/19 – 2,065

 

Approval Status

Business case approved

Delivery Status

Completed

Last updated: August 14, 2019