This project will deliver W10 & W12 gauge enhancements on the South Bank line between Immingham & Doncaster, enabling the larger ‘high cube’ containers to be transported by rail.

CASE STUDY – South Humber Rail Gauge Enhancements  PHOTOS – South Humber Rail Gauge Enhancements

By around 2020 more than 50% of containers arriving at our UK ports will be on ‘high cube’ containers. We are currently not able to transport them out of the South Humber ports, where our rail infrastructure only supports standard containers.

‘High cube’ containers are 9’6” in measurement and therefore limitations currently involve height & width restrictions to bridges, tunnels, platforms & other structures.

Project Dates

September 1, 2018 - June 30, 2019

Project Sponsor

Location

South Humber Ports to Doncaster

Funding

Total Project Expenditure: £17,199,000

LGF Spend:

    • Contracted:  £7,200,000
    • Achieved to date – £7,200,000.00

Public Spend:

    • Contracted: £9,999,000
    • Achieved to date – £9,999,000

Outputs

Construction Jobs:

    • Contracted: 50
    • Achieved to date – 70

W12 Gauge Certificate:

    • Contracted: 1
    • Achieved to date – 1

Approval Status

Delivery Status

View project homepage

Last updated: May 29, 2020