This project will deliver W10 & W12 gauge enhancements on the South Bank line between Immingham & Doncaster, enabling the larger ‘high cube’ containers to be transported by rail.

 

 

 

 

 

 

 

 

 

CASE STUDY – South Humber Rail Gauge Enhancements  PHOTOS – South Humber Rail Gauge Enhancements

By around 2020 more than 50% of containers arriving at our UK ports will be on ‘high cube’ containers. We are currently not able to transport them out of the South Humber ports, where our rail infrastructure only supports standard containers.

‘High cube’ containers are 9’6” in measurement and therefore limitations currently involve height & width restrictions to bridges, tunnels, platforms & other structures.

Project Dates

January 4, 2016 - July 3, 2021

Project Sponsor

North Lincolnshire Council

Location

South Humber Ports to Doncaster

Funding

Total Project Expenditure: £17,199,000

  • LGF Spend:
    • Contracted:  £7,200,000
    • Achieved: 2015/17 – £2,145,000
    • Achieved: 2017/18 – £0
    • Achieved: 2018/19 – £4,055,000
  • Public Spend:
    • Contracted: £9,999,000
    • Achieved: 2015/17 – £1,171,693
    • Achieved: 2017/18 – £573,124
    • Achieved: 2018/19 – £8,116,183

Outputs

  • Construction Jobs:
    • Contracted: 50
    • Achieved: 0
  • W12 Gauge Certificate:
    • Contracted: 1
    • Achieved: 0

Approval Status

Business case approved

Delivery Status

Started

Last updated: August 14, 2019