Tags: Growth Deal, Local Growth Fund, Northern Powerhouse

The Goole College Skills Workshop Modernisation and Logistics Hub scheme is a part extension, part refurbishment scheme to double the size of the engineering and construction skills workshop at Boothferry Road in Goole and to refurbish a derelict part of the college building to provide a logistics and health and safety hub, incorporating a CSCS card assessment centre.

CASE STUDY – Goole College  PHOTOS – Goole College

Project Dates

August 3, 2015 - August 26, 2016

Project Sponsor

Hull College Group

Location

Boothferry Road, Goole, East Riding of Yorkshire DN14 6SR

Funding

Figures updated 8/7/2019

Project cost – £554,921

  • LGF Spend – £375,000
  • Public Spend – £179,921

 

Outputs

Outputs and Numbers updated 8/7/2019

Outputs/Numbers

  • New Jobs:
    • Contracted – 2
    • Achieved: Pre 2018/19 – 0
    • Achieved: 2018/19 – 2
  • Completed new build training/learning floor space (sq.m.):
    • Contracted – 190
    • Achieved – Pre 2018/19 – 270
    • Achieved – 2018/29 – 0
  • Completed refurbished build training/learning floor space (sq.m.):
    • Contracted – 190
    • Achieved – Pre 2018/19 – 87
    • Achieved – 2018/19 – 0
  • Level 1 qualifications:
    • Contracted – 101
    • Achieved Pre 2018/19 – 57
    • Achieved 2018/19 – 14
  • Level 2 qualifications:
    • Contracted – 96
    • Achieved Pre 2018/19 – 62
    • Achieved 2018/19 – 10
  • Level 3 qualifications:
    • Contracted – 83
    • Achieved Pre 2018/19 – 54
    • Achieved 2018/19 – 9
  • Level 4 qualifications:
    • Contracted – 36
    • Achieved Pre 2018/19 – 20
    • Achieved 2018/19 – 0
  • 16-18yr olds (Intermediate) Apprenticeships:
    • Contracted – 25
    • Achieved Pre 2018/19 – 15
    • Achieved 2018/19 – 0
  • 16-18yr olds (Advanced) Apprenticeships:
    • Contracted – 15
    • Achieved Pre 2018/19 – 5
    • Achieved 2018/19 – 0
  • Adult (19+) (Highers) Apprenticeships:
    • Contracted – 5
    • Achieved Pre 2018/19 – 0
    • Achieved 2018/19 – 0

Approval Status

Business case approved

Delivery Status

Completed

View project homepage

Last updated: July 8, 2019