Existing defences along the River Hull are in a poor state of repair, with Environment Agency data showing a 60% probability of breach or overtopping at various locations.  This project provides improvements which protect existing homes, businesses (mostly SMEs) and critical infrastructure, and enables future growth both on the 11 Enterprise Zone sites along the River Hull corridor and in housing.

 

 

 

 

 

 

 

 

 

 

 

 

CASE STUDY – River Hull Defences PHOTOS – River Hull Defences

Project Dates

November 1, 2016 - July 9, 2020

Project Sponsor

Hull City Council

Location

River Hull

Funding

Total project expenditure – £31,994,976.00

LGF Spend:

  • Contracted – £1,000,000.00
  • Achieved 2017/18 – £1,000,000.00

Public Spend:

  • Contracted – £30,994,976.00
  • Achieved 2015/17 – £1,640,860.00
  • Achieved 2017/18 – £11,456,044.00
  • Achieved 2018/19 – £15,013,714.00

 

Outputs

Construction Jobs:

  • Contracted – 150
  • Achieved to date – 0

Area of land with reduced flood risk (ha):

  • Contracted – 5,546
  • Achieved to date – 0

Domestic properties with reduced flood risk:

  • Contracted – 1,179
  • Achieved to date – 0

Commercial floor space with reduced flood risk (sq.m.):

  • Contracted – 400,000
  • Achieved to date – 0

Approval Status

Business case approved

Delivery Status

Started

Last updated: August 13, 2019