The project supports Hull City Centre’s transition to new leisure and residential uses. This will be achieved through delivering key development sites and supporting the conversion of empty properties where their traditional use is no longer viable. The project addresses viability issues caused by land conditions, archaeology, contamination, access infrastructure and flood risk.
Project Dates
April 1, 2017 - March 31, 2020
Project Sponsor
Hull City Council
Location
Hull city centre
Funding
Total project expenditure – £10,613,374.00
LGF Spend:
- Contracted – £2,500,000.00
- Achieved to date – £455,470.00
Public Spend:
- Contracted – £8,113,374.00
- Achieved to date – £5,104,376.00
Outputs
Area of land reclaimed/redeveloped or reassembled (ha):
- Contracted – 0.89
- Achieved to date – 0.89
Buildings demolished:
- Contracted – 2
- Achieved to date – 0
Buildings cleared of asbestos:
- Contracted – 2
- Achieved to date – 0
Approval Status
Business case approved
Delivery Status
Started
View project homepageAll locations are approximate.